The precedence relations and durations of jobs in a project are given below:
Job Predecessor(s) Duration (in days) A - 2 B - 4 C A 6 D A 8 E B,C 6 F B,C 4 G F 2 H F 8 I D,E,G 6
(b) Determine all critical path(s) and their duration(s).
(c) What is the total float for jobs B and D?
[5 marks]